Progress continues on the new school at 280 Marker
Road. At this point in the construction process nearly all foundation
footers are poured with the exception of the theater and the kitchen.
The kitchen footers will be poured later this summer. The storm sewer,
sanitary sewer and water lines have been run to the building. The high
school gym walls are in place as is the theater stage. Work is
progressing on the elementary/middle school gym walls and in parts of
the library. Soon bar joists will be set in the gym areas with the roof
deck to follow. Plumbing has been roughed in and the electricians are
working with the masons as they progress. |
|
|
|